Chinese New Year 2027 falls on Saturday, February 6, 2027, and the practical cut-off to confirm a carpet or rug order that ships before the holiday is early December 2026; orders confirmed after about December 20 usually ship in early-to-mid March. Chinese New Year (CNY) is the single biggest disruption in the China sourcing calendar. For two to four weeks, most factories stop completely, and production capacity is reduced for weeks before and after. If your spring stock depends on an order from China, the decisions you make in November and early December decide whether it arrives in February or in April.
This guide covers the 2027 dates, the realistic order cut-off for carpets and rugs, and how to plan around the shutdown. It is based on our experience working with carpet factories in Tianjin.
| Date | What happens |
|---|---|
| Early December 2026 | Practical order cut-off to ship before the holiday |
| Mid-January 2027 | Workers start travelling home; output slows. Vessel space and trucks get tight |
| Late January 2027 | Most factories stop production |
| Saturday, February 6, 2027 | Chinese New Year's Day (Year of the Goat) |
| Mid-February 2027 | Official holiday ends; offices reopen, factories restart gradually |
| Saturday, February 20, 2027 | Lantern Festival. Many factories reach normal staffing only after this date |
| March 2027 | Post-holiday backlog; lead times longer than usual |
The State Council publishes the exact official holiday schedule each year, usually in November. Factory shutdowns are almost always longer than the official holiday because workers travel long distances to their home provinces.
Carpet production takes about 25-35 days after the order is confirmed, plus a few days for pre-shipment inspection and loading. Working back from a mid-January loading date gives this picture:
| Order confirmed by | Expected result |
|---|---|
| Early December 2026 | Production finishes in early-to-mid January; ships before the holiday |
| Early to late December 2026 | Possible but tight. Depends on product, quantity and factory load |
| After about December 20, 2026 | Usually ships after the holiday, around early-to-mid March 2027 |
"Confirmed" means all three: deposit paid, sample or specification approved, and artwork and packaging finalised. An order still waiting on a sample approval or a label file is not in the production queue yet. Most pre-holiday delays come from this, not from the factory.
If you have never ordered from us, add time for a sample: usually 7-15 days to make it plus courier time. See our sample order guide. For a first order, the realistic plan is to approve samples before the holiday and place the bulk order to run immediately after it.
Orders placed in late January or February usually start production only once the backlog clears, so expect lead times to run one to two weeks longer than normal through March.
Quality needs extra attention too. New workers on the first runs of the year are the main risk for things like uneven pile height, print registration and edge binding. For any order produced in late February or March:
Planning ahead for Q4 2027? The CNY shutdown is also the best time to brief seasonal designs. Send artwork in January and samples can start as soon as the factory reopens. See our Christmas & holiday rugs planning guide.
Our partner factories in Tianjin Wuqing produce printed carpets, faux fur rugs, shaggy rugs, bath mats and kitchen mats, with MOQ from 50 pieces (see MOQ explained). Tell us your products, quantities and target arrival date, and we will confirm whether your order can ship before Chinese New Year.
Chinese New Year (Spring Festival) 2027 falls on Saturday, February 6, 2027, the start of the Year of the Goat. The official public holiday lasts about a week, but most manufacturing slows from mid-January and many factories do not return to full capacity until after the Lantern Festival on February 20, 2027, or later.
To ship before the holiday, the order should be confirmed, with the deposit paid and the sample approved, by early December 2026. Carpet production takes about 25-35 days plus inspection and booking, so goods can load in mid-to-late January before factories and trucking slow down. Orders confirmed between early and late December are possible but tight. Orders confirmed after about December 20 will usually ship after the holiday, in early-to-mid March 2027.
Most factories stop production about one week before the holiday and restart one to two weeks after it, so the total shutdown is typically two to four weeks. Production often runs at reduced capacity for several more weeks while workers return and new staff are trained. For 2027, expect most factories to be closed from late January to mid/late February.
Yes. In the two to four weeks before the holiday, many exporters try to ship at once, so vessel space gets tight and freight rates often rise. Book container space with your forwarder as soon as your production completion date is confirmed. Ports keep operating during the holiday, but trucking, customs brokers and inspection companies run with reduced staff.
It can be. Some workers do not return after the holiday, so factories train new staff on the first production runs of the year. For orders produced in late February and March, insist on an approved pre-production sample and a pre-shipment inspection based on AQL sampling, and confirm that the same materials and specifications as your previous order are used.